Dept. of Trans. PROGRESS Serial No. Contract No. 21-077-08-46 01-0F4404 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 93% Location: Federal Project: 01-MEN-1-0.0/15.0 NONE Progress payment No. 006 Payment period ending: 03-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,293,462.98 284,058.90 2. a. Extra Work 219,708.97 214,316.77 b. Adustment Comp. 12,878.57 -10,577.43 3. Materials on Hand 4. Earned Subject to Retention 9,526,050.52 487,798.24 5. Mobilization 932,000.00 0.00 6. Total Work Completed 10,458,050.52 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,458,050.52 487,798.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 487,798.24