Dept. of Trans. PROGRESS Serial No. Contract No. 21-327-13-38 01-0F4604 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 84% Location: Federal Project: 01-HUM-299-20.5/30.2 HSST-P299(208) Progress payment No. 012 Payment period ending: 11-20-21 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,774,578.11 25,935.37 2. a. Extra Work 78,755.72 7,753.88 b. Adustment Comp. -10,000.00 -10,000.00 3. Materials on Hand 4. Earned Subject to Retention 3,843,333.83 23,689.25 5. Mobilization 588,960.00 0.00 6. Total Work Completed 4,432,293.83 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 48,009.48 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,429,293.83 68,698.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,698.73