Dept. of Trans. PROGRESS Serial No. Contract No. 22-332-14-50 01-0F5304 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 100% Location: Federal Project: 01-HUM-299-R1.8/R1.8 NONE 01-HUM-200-R2.7/R2.7 Progress payment No. 007 Payment period ending: 11-20-22 STEELHEAD CONSTRUCTORS JV PO BOX 536 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,445,988.41 571,610.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,445,988.41 571,610.00 5. Mobilization 313,500.00 0.00 6. Total Work Completed 1,759,488.41 7. Deductions -394,000.00 -386,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -73,540.65 -57,161.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,291,947.76 128,449.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 128,449.00