Dept. of Trans. PROGRESS Serial No. Contract No. 17-205-11-39 01-0G1904 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 100% Location: Federal Project: 01-MEN-1-82.0/82.0 NONE Progress payment No. 004 Payment period ending: 07-20-17 BUD GARMAN CONSTRUCTION INC 389 N MAIN ST WILLITS CA 95490 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 739,585.36 210,671.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 739,585.36 210,671.40 5. Mobilization 6. Total Work Completed 739,585.36 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 739,585.36 210,671.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 210,671.40