Dept. of Trans. PROGRESS Serial No. Contract No. 17-270-13-13 01-0G1904 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 0% Location: Federal Project: 01-MEN-1-82.0/82.0 NONE Progress payment No. 006 Payment period ending: 09-20-17 BUD GARMAN CONSTRUCTION INC 389 N MAIN ST WILLITS CA 95490 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 992,857.37 64,912.01 b. Adustment Comp. -6,975.05 -6,975.05 3. Materials on Hand 4. Earned Subject to Retention 985,882.32 57,936.96 5. Mobilization 6. Total Work Completed 985,882.32 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 985,882.32 57,936.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,936.96