Dept. of Trans. PROGRESS Serial No. Contract No. 16-259-14-53 01-0G2404 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 100% Location: Federal Project: 01-HUM-299-26.2/26.3 NONE Progress payment No. 002 Payment period ending: 05-12-16 6 RIVERS CONSTRUCTION INC PO BOX 1431 HOOPA CA 95546 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,313.00 7,313.00 2. a. Extra Work 228,353.81 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 235,666.81 7,313.00 5. Mobilization 6. Total Work Completed 235,666.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 235,666.81 7,313.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,313.00