Dept. of Trans. PROGRESS Serial No. Contract No. 21-232-16-44 01-0G4304 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 35% Location: Federal Project: 01-MEN-20-24.6/24.8 HSST-P020(192) Progress payment No. 002 Payment period ending: 08-20-21 REGE CONSTRUCTION, INC. 600 SANTANA DRIVE CLOVERDALE CA 95425 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,040,458.15 865,593.31 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,040,458.15 865,593.31 5. Mobilization 130,662.00 65,331.00 6. Total Work Completed 1,171,120.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,171,120.15 930,924.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 930,924.31