Dept. of Trans. PROGRESS Serial No. Contract No. 21-125-09-42 01-0G6504 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 01-MEN-101-104.7/105.3 NONE Progress payment No. 036 Payment period ending: 12-29-20 MENDOCINO CONSTRUCTION SVC INC PO BOX 1517 WILLITS CA 95490 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,506.00 6,506.00 2. a. Extra Work 11,456,434.04 105,006.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 11,462,940.04 111,512.00 5. Mobilization 6. Total Work Completed 11,462,940.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,462,940.04 111,512.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 111,512.00