Dept. of Trans. PROGRESS Serial No. Contract No. 20-171-14-48 01-0G7004 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 9% Location: Federal Project: 01-LAK-20-28.4/28.4 NONE Progress payment No. 002 Payment period ending: 06-20-20 ROBERT J FRANK CONSTRUCTION INC 2806 TARMAC RD REDDING CA 96003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 167,654.00 81,940.00 2. a. Extra Work b. Adustment Comp. -8,000.00 -8,000.00 3. Materials on Hand 4. Earned Subject to Retention 159,654.00 73,940.00 5. Mobilization 17,100.00 0.00 6. Total Work Completed 176,754.00 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 174,754.00 71,940.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,940.00