Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-10-22 01-0G7404 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 79% Location: Federal Project: 01-HUM-999 ACST-X023(39) Progress payment No. 003 Payment period ending: 11-20-18 S.T. RHOADES CONSTRUCTION INC. PO BOX 494520 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 867,726.09 205,247.10 2. a. Extra Work 4,671.62 4,671.62 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 872,397.71 209,918.72 5. Mobilization 6. Total Work Completed 872,397.71 7. Deductions -5,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 867,397.71 210,918.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 210,918.72