Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-080-15-10 01-0G8004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-MEN-1-78.0/83.5 NONE Progress payment No. 028 Payment period ending: 09-26-18 MCM CONSTRUCTION INC 6413 32ND ST NO HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,500.00 0.00 2. a. Extra Work 8,418,771.18 -4,467.90 b. Adustment Comp. -74,839.29 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,357,431.89 -4,467.90 5. Mobilization 6. Total Work Completed 8,357,431.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,357,431.89 -4,467.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -4,467.90