Dept. of Trans. PROGRESS Serial No. Contract No. 17-207-14-33 01-0G8904 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 67% Location: Federal Project: 01-MEN-1-38.5/40.5 NONE Progress payment No. 003 Payment period ending: 07-14-17 PAULSON EXCAVATING INC 32700 ALBION RIDGE RD ALBION CA 95410 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 252,707.86 8,959.98 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 252,707.86 8,959.98 5. Mobilization 6. Total Work Completed 252,707.86 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 252,707.86 9,959.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,959.98