Dept. of Trans. PROGRESS Serial No. Contract No. 24-113-10-14 01-0H1604 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 64% Location: Federal Project: 01-MEN-101-R33.7/R43.2 ACNH-Q101(416) Progress payment No. 010 Payment period ending: 04-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,770,650.79 360,130.05 2. a. Extra Work 274,529.63 0.00 b. Adustment Comp. 148,172.80 0.00 3. Materials on Hand 156,534.00 -146,315.00 4. Earned Subject to Retention 18,349,887.22 213,815.05 5. Mobilization 1,727,000.00 0.00 6. Total Work Completed 19,920,353.22 7. Deductions -42,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,034,887.22 213,815.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 213,815.05