Dept. of Trans. PROGRESS Serial No. Contract No. 25-176-09-39 01-0H1604 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 98% Location: Federal Project: 01-MEN-101-R33.7/R43.2 ACNH-Q101(416) Progress payment No. 022 Payment period ending: 06-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,419,099.58 0.00 2. a. Extra Work 917,641.84 136,814.69 b. Adustment Comp. 177,392.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,514,134.12 136,814.69 5. Mobilization 1,727,000.00 0.00 6. Total Work Completed 23,241,134.12 7. Deductions -34,203.00 -34,203.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,206,931.12 102,611.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,611.69