Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 23-214-15-54 01-0H20U4 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 23% Location: Federal Project: 01-HUM-101-75.9/79.5 HSNH-Q101(413) Progress payment No. 005 Payment period ending: 07-20-23 S.T. RHOADES CONSTRUCTION INC. 8585 COMMERCIAL WAY REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,026,373.41 334,444.45 2. a. Extra Work 16,558.21 0.00 b. Adustment Comp. 3. Materials on Hand 59,583.38 59,583.38 4. Earned Subject to Retention 2,102,515.00 394,027.83 5. Mobilization 745,500.00 0.00 6. Total Work Completed 2,788,431.62 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,838,015.00 394,027.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 394,027.83