Dept. of Trans. PROGRESS Serial No. Contract No. 24-115-08-37 01-0H4314 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 3% Location: Federal Project: 01-HUM-299-R11.0/R11.4 ER-31S3(4) Progress payment No. 002 Payment period ending: 04-20-24 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 310,222.30 279,677.30 2. a. Extra Work 54,306.69 53,252.49 b. Adustment Comp. 3. Materials on Hand 64,605.10 -38,988.60 4. Earned Subject to Retention 429,134.09 293,941.19 5. Mobilization 385,065.00 385,065.00 6. Total Work Completed 749,593.99 7. Deductions -93,845.26 -93,845.26 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 720,353.83 585,160.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 585,160.93