Dept. of Trans. PROGRESS Serial No. Contract No. 22-263-09-10 01-0H45U4 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 33% Location: Federal Project: 01-MEN-20-19.1/20.3 HSST-P020(200) Progress payment No. 002 Payment period ending: 09-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 460,550.32 228,319.90 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 460,550.32 228,319.90 5. Mobilization 213,789.00 71,263.00 6. Total Work Completed 674,339.32 7. Deductions -8,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 666,339.32 291,582.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 291,582.90