Dept. of Trans. PROGRESS Serial No. Contract No. 23-054-15-17 01-0H45U4 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 84% Location: Federal Project: 01-MEN-20-19.1/20.3 HSST-P020(200) Progress payment No. 006 Payment period ending: 02-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,931,195.62 1,153.54 2. a. Extra Work 222,580.43 59,509.10 b. Adustment Comp. -170,654.25 2,968.78 3. Materials on Hand 4. Earned Subject to Retention 1,983,121.80 63,631.42 5. Mobilization 285,052.00 0.00 6. Total Work Completed 2,268,173.80 7. Deductions -12,000.00 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,256,173.80 67,631.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,631.42