Dept. of Trans. PROGRESS Serial No. Contract No. 23-080-17-08 01-0H45U4 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 95% Location: Federal Project: 01-MEN-20-19.1/20.3 HSST-P020(200) Progress payment No. 007 Payment period ending: 03-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,934,695.62 3,500.00 2. a. Extra Work 222,580.43 0.00 b. Adustment Comp. -170,654.25 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,986,621.80 3,500.00 5. Mobilization 285,052.00 0.00 6. Total Work Completed 2,271,673.80 7. Deductions -2,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -350.00 -350.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,269,323.80 13,150.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,150.00