Dept. of Trans. PROGRESS Serial No. Contract No. 23-235-10-21 01-0H45U4 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 95% Location: Federal Project: 01-MEN-20-19.1/20.3 HSST-P020(200) Progress payment No. 011 Payment period ending: 08-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,653,706.20 49,502.12 2. a. Extra Work 310,525.44 0.00 b. Adustment Comp. -174,955.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,789,276.50 49,502.12 5. Mobilization 285,052.00 0.00 6. Total Work Completed 3,074,328.50 7. Deductions -10,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,064,328.50 43,502.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,502.12