Dept. of Trans. PROGRESS Serial No. Contract No. 23-262-11-54 01-0H45U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 95% Location: Federal Project: 01-MEN-20-19.1/20.3 HSST-P020(200) Progress payment No. 012 Payment period ending: 09-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,838,099.93 184,393.73 2. a. Extra Work 365,211.94 54,686.50 b. Adustment Comp. -174,955.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,028,356.73 239,080.23 5. Mobilization 285,052.00 0.00 6. Total Work Completed 3,313,408.73 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,303,408.73 239,080.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 239,080.23