Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-11-21 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 3% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 003 Payment period ending: 04-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,143,075.65 259,397.75 2. a. Extra Work 3,960.00 3,960.00 b. Adustment Comp. -2,874.68 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,144,160.97 263,357.75 5. Mobilization 1,145,000.00 1,145,000.00 6. Total Work Completed 2,289,160.97 7. Deductions -5,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,284,160.97 1,413,357.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,413,357.75