Dept. of Trans. PROGRESS Serial No. Contract No. 25-140-14-59 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 3% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 004 Payment period ending: 05-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,445,076.06 302,000.41 2. a. Extra Work 18,079.28 14,119.28 b. Adustment Comp. -20,261.55 -17,386.87 3. Materials on Hand 4. Earned Subject to Retention 1,442,893.79 298,732.82 5. Mobilization 1,145,000.00 0.00 6. Total Work Completed 2,587,893.79 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,582,893.79 298,732.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 298,732.82