Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-13-24 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 39% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 007 Payment period ending: 08-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,872,861.16 2,459,694.87 2. a. Extra Work 304,083.31 62,131.29 b. Adustment Comp. -134,076.43 -22,505.27 3. Materials on Hand 4. Earned Subject to Retention 9,042,868.04 2,499,320.89 5. Mobilization 2,175,500.00 0.00 6. Total Work Completed 11,218,368.04 7. Deductions -20,000.00 -13,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,198,368.04 2,486,320.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,486,320.89