Dept. of Trans. PROGRESS Serial No. Contract No. 25-261-11-51 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 49% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 008 Payment period ending: 09-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,519,166.57 6,646,305.41 2. a. Extra Work 329,019.07 24,935.76 b. Adustment Comp. -273,634.34 -139,557.91 3. Materials on Hand 4. Earned Subject to Retention 15,574,551.30 6,531,683.26 5. Mobilization 2,290,000.00 114,500.00 6. Total Work Completed 17,864,551.30 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,844,551.30 6,646,183.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,646,183.26