Dept. of Trans. PROGRESS Serial No. Contract No. 25-356-11-49 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 66% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 011 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,576,485.43 994,468.79 2. a. Extra Work 559,354.78 20,038.39 b. Adustment Comp. -483,447.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 17,652,392.28 1,014,507.18 5. Mobilization 2,290,000.00 0.00 6. Total Work Completed 19,942,392.28 7. Deductions -187,109.37 -146,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,755,282.91 868,507.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 868,507.18