Dept. of Trans. PROGRESS Serial No. Contract No. 26-051-14-01 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 68% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 013 Payment period ending: 02-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,481,016.25 324,367.36 2. a. Extra Work 791,327.57 127,288.20 b. Adustment Comp. -483,447.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,788,895.89 451,655.56 5. Mobilization 2,290,000.00 0.00 6. Total Work Completed 21,078,895.89 7. Deductions -47,109.37 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,031,786.52 454,655.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 454,655.56