Dept. of Trans. PROGRESS Serial No. Contract No. 26-079-09-23 01-0H5504 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 97% Location: Federal Project: 01-MEN-101-55.0/64.9 ACNH-Q101(427) Progress payment No. 014 Payment period ending: 03-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,490,916.25 9,900.00 2. a. Extra Work 978,396.32 187,068.75 b. Adustment Comp. -354,675.47 128,772.46 3. Materials on Hand 4. Earned Subject to Retention 19,114,637.10 325,741.21 5. Mobilization 2,290,000.00 0.00 6. Total Work Completed 21,404,637.10 7. Deductions -19,109.37 28,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,385,527.73 353,741.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 353,741.21