Dept. of Trans. PROGRESS Serial No. Contract No. 23-331-14-26 01-0H5604 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 29% Location: Federal Project: 01-HUM-299-0.0/R5.7 ACNH-P299(215) Progress payment No. 002 Payment period ending: 11-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 232,341.76 208,116.76 2. a. Extra Work b. Adustment Comp. 33,372.00 33,372.00 3. Materials on Hand 4. Earned Subject to Retention 265,713.76 241,488.76 5. Mobilization 6. Total Work Completed 265,713.76 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 259,713.76 235,488.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 235,488.76