Dept. of Trans. PROGRESS Serial No. Contract No. 24-082-10-49 01-0H5604 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 9% Location: Federal Project: 01-HUM-299-0.0/R5.7 ACNH-P299(215) Progress payment No. 006 Payment period ending: 03-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,237,698.78 510,304.11 2. a. Extra Work b. Adustment Comp. 33,372.00 0.00 3. Materials on Hand 139,160.00 -22,773.00 4. Earned Subject to Retention 1,410,230.78 487,531.11 5. Mobilization 825,750.00 275,250.00 6. Total Work Completed 2,096,820.78 7. Deductions -9,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,226,980.78 754,781.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 754,781.11