Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-10-57 01-0H5804 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 97% Location: Federal Project: 01-HUM-299-R7.6/R29.2 ACNH-P299(216) Progress payment No. 012 Payment period ending: 06-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,015,539.84 2,082,723.27 2. a. Extra Work 130,507.95 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,146,047.79 2,082,723.27 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 13,536,047.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,536,047.79 2,082,723.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,082,723.27