Dept. of Trans. PROGRESS Serial No. Contract No. 25-168-10-25 01-0H8404 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 73% Location: Federal Project: 01-LAK-20-2.0/2.8 HSST-P020(201) Progress payment No. 021 Payment period ending: 06-20-25 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,540,456.04 924,052.06 2. a. Extra Work 97,523.65 0.00 b. Adustment Comp. 82,626.80 0.00 3. Materials on Hand 98,765.40 -565.04 4. Earned Subject to Retention 11,819,371.89 923,487.02 5. Mobilization 1,310,000.00 0.00 6. Total Work Completed 13,030,606.49 7. Deductions -14,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,115,371.89 923,487.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 923,487.02