Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-06-11 01-0H8404 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 97% Location: Federal Project: 01-LAK-20-2.0/2.8 HSST-P020(201) Progress payment No. 025 Payment period ending: 10-20-25 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,077,796.00 541,870.79 2. a. Extra Work 107,894.65 4,571.00 b. Adustment Comp. 69,529.20 -4,378.98 3. Materials on Hand 4. Earned Subject to Retention 14,255,219.85 542,062.81 5. Mobilization 1,310,000.00 0.00 6. Total Work Completed 15,565,219.85 7. Deductions -50,531.40 -34,531.40 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,514,688.45 507,531.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 507,531.41