Dept. of Trans. PROGRESS Serial No. Contract No. 23-201-16-34 01-0J4104 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 13% Location: Federal Project: 01-HUM-299-30.7/33.4 HSNH-P299(214) Progress payment No. 003 Payment period ending: 07-20-23 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,957,337.00 1,035,666.83 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 110,717.06 -252,202.14 4. Earned Subject to Retention 2,068,054.06 783,464.69 5. Mobilization 816,555.00 272,185.00 6. Total Work Completed 2,773,892.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,884,609.06 1,055,649.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,055,649.69