Dept. of Trans. PROGRESS Serial No. Contract No. 24-263-15-34 01-0J4104 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 62% Location: Federal Project: 01-HUM-299-30.7/33.4 HSNH-P299(214) Progress payment No. 017 Payment period ending: 09-20-24 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,959,206.67 2,145,463.14 2. a. Extra Work 72,532.73 30,046.00 b. Adustment Comp. 3. Materials on Hand 231,266.77 -303,166.18 4. Earned Subject to Retention 10,263,006.17 1,872,342.96 5. Mobilization 1,088,740.00 54,437.00 6. Total Work Completed 11,120,479.40 7. Deductions 0.00 13,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,351,746.17 1,939,779.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,939,779.96