Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-13-30 01-0J4104 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 70% Location: Federal Project: 01-HUM-299-30.7/33.4 HSNH-P299(214) Progress payment No. 020 Payment period ending: 12-20-24 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,030,480.58 276,144.93 2. a. Extra Work 147,593.95 9,346.63 b. Adustment Comp. 3. Materials on Hand 136,978.87 0.00 4. Earned Subject to Retention 12,315,053.40 285,491.56 5. Mobilization 1,088,740.00 0.00 6. Total Work Completed 13,266,814.53 7. Deductions -15,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,388,793.40 280,491.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 280,491.56