Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-13-59 01-0J4504 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 9% Location: Federal Project: 01-HUM-101-80.0 NONE Progress payment No. 004 Payment period ending: 05-20-19 WAHLUND CONSTRUCTION INC 830 HILMA DR EUREKA CA 95503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 267,441.11 6,859.01 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 267,441.11 6,859.01 5. Mobilization 6. Total Work Completed 267,441.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 267,441.11 6,859.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,859.01