Dept. of Trans. PROGRESS Serial No. Contract No. 19-347-08-47 01-0J5704 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 50% Location: Federal Project: 01-DN-199-335.0/33.9 NONE Progress payment No. 004 Payment period ending: 12-06-19 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 809,537.55 144,487.58 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 809,537.55 144,487.58 5. Mobilization 6. Total Work Completed 809,537.55 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 806,537.55 141,487.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 141,487.58