Dept. of Trans. PROGRESS Serial No. Contract No. 24-115-08-48 01-0J6314 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 10% Location: Federal Project: 01-MEN-253-1.6/2.2 ACST-ER(39A) Progress payment No. 003 Payment period ending: 04-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,183,232.63 1,030,315.83 2. a. Extra Work 145,845.23 66,420.23 b. Adustment Comp. 3. Materials on Hand 159,373.86 -155,770.22 4. Earned Subject to Retention 1,488,451.72 940,965.84 5. Mobilization 667,500.00 222,500.00 6. Total Work Completed 1,996,577.86 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,145,951.72 1,153,465.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,153,465.84