Dept. of Trans. PROGRESS Serial No. Contract No. 24-142-12-42 01-0J6314 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 20% Location: Federal Project: 01-MEN-253-1.6/2.2 ACST-ER(39A) Progress payment No. 004 Payment period ending: 05-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,954,004.51 770,771.88 2. a. Extra Work 148,120.60 2,275.37 b. Adustment Comp. 3. Materials on Hand 48,390.62 -110,983.24 4. Earned Subject to Retention 2,150,515.73 662,064.01 5. Mobilization 845,500.00 178,000.00 6. Total Work Completed 2,947,625.11 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,986,015.73 840,064.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 840,064.01