Dept. of Trans. PROGRESS Serial No. Contract No. 24-239-08-47 01-0J6314 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 46% Location: Federal Project: 01-MEN-253-1.6/2.2 ACST-ER(39A) Progress payment No. 007 Payment period ending: 08-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,530,644.64 561,415.50 2. a. Extra Work 161,022.12 8,281.75 b. Adustment Comp. 3. Materials on Hand 48,147.64 -56,454.75 4. Earned Subject to Retention 3,739,814.40 513,242.50 5. Mobilization 845,500.00 0.00 6. Total Work Completed 4,537,166.76 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,584,314.40 512,242.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 512,242.50