Dept. of Trans. PROGRESS Serial No. Contract No. 24-262-15-04 01-0J6314 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 59% Location: Federal Project: 01-MEN-253-1.6/2.2 ACST-ER(39A) Progress payment No. 008 Payment period ending: 09-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,666,243.58 1,135,598.94 2. a. Extra Work 197,925.53 36,903.41 b. Adustment Comp. 3. Materials on Hand 43,448.70 -4,698.94 4. Earned Subject to Retention 4,907,617.81 1,167,803.41 5. Mobilization 890,000.00 44,500.00 6. Total Work Completed 5,754,169.11 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,797,617.81 1,213,303.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,213,303.41