Dept. of Trans. PROGRESS Serial No. Contract No. 24-358-10-56 01-0J6314 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 82% Location: Federal Project: 01-MEN-253-1.6/2.2 ACST-ER(39A) Progress payment No. 011 Payment period ending: 12-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,257,432.23 346,171.75 2. a. Extra Work 231,810.28 23,188.71 b. Adustment Comp. 72,477.44 -8,000.00 3. Materials on Hand 4. Earned Subject to Retention 7,561,719.95 361,360.46 5. Mobilization 890,000.00 0.00 6. Total Work Completed 8,451,719.95 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,449,719.95 359,360.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,360.46