Dept. of Trans. PROGRESS Serial No. Contract No. 19-141-10-19 01-0J6604 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 20% Location: Federal Project: 01-HUM-169-33.7 NONE Progress payment No. 002 Payment period ending: 05-20-19 KAPEL CONSTRUCTION INC. PO BOX 160 BURNT RANCH CA 95527 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 249,184.10 96,697.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 249,184.10 96,697.07 5. Mobilization 6. Total Work Completed 249,184.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 249,184.10 96,697.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,697.07