Dept. of Trans. PROGRESS Serial No. Contract No. 19-171-11-38 01-0J7004 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 2% Location: Federal Project: 01-MEN-20-35.4 NONE Progress payment No. 001 Payment period ending: 06-20-19 BOUTHILLIER'S CONSTRUCTION INC 1571 SOUTH MAIN ST WILLITS CA 95490 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 45,195.30 45,195.30 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 45,195.30 45,195.30 5. Mobilization 6. Total Work Completed 45,195.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 45,195.30 45,195.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,195.30