Dept. of Trans. PROGRESS Serial No. Contract No. 19-238-09-24 01-0J7104 PROGRESS PAYMENT VOUCHER %complete: %time: 5% 19% Location: Federal Project: 01-MEN-101-36.0/38.0 NONE Progress payment No. 003 Payment period ending: 08-20-19 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 709,465.72 25,965.51 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 709,465.72 25,965.51 5. Mobilization 6. Total Work Completed 709,465.72 7. Deductions -6,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 703,465.72 25,965.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,965.51