Dept. of Trans. PROGRESS Serial No. Contract No. 19-255-14-04 01-0J7304 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 0% Location: Federal Project: 01-MEN-1-18.0/23.0 NONE Progress payment No. 003 Payment period ending: 09-06-19 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 325,987.96 151,963.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 325,987.96 151,963.52 5. Mobilization 6. Total Work Completed 325,987.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 325,987.96 151,963.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,963.52