Dept. of Trans. PROGRESS Serial No. Contract No. 19-357-15-17 01-0J8504 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 5% Location: Federal Project: 01-MEN-128-427.0 NONE Progress payment No. 003 Payment period ending: 12-20-19 BUD GARMAN CONSTRUCTION SERVICES INC 24900 N HWY 101 WILLITS CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 349,595.34 176,454.81 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 349,595.34 176,454.81 5. Mobilization 6. Total Work Completed 349,595.34 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 349,595.34 176,454.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,454.81