Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-11-37 01-0K6404 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 53% Location: Federal Project: 01-DN-199-24.1/24.3 HSNH-P199(40) Progress payment No. 001 Payment period ending: 09-20-24 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 171,759.20 171,759.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 171,759.20 171,759.20 5. Mobilization 63,750.00 63,750.00 6. Total Work Completed 235,509.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 235,509.20 235,509.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 235,509.20