Dept. of Trans. SEMI-FINAL Serial No. Contract No. 23-338-14-09 01-0K8804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-HUM-101-94.9/122.0 NONE Progress payment No. 002 Payment period ending: 08-22-23 R BROWN CONSTRUCTION CO INC PO BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 353,491.00 5,640.00 2. a. Extra Work 5,649.97 5,649.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 359,140.97 11,289.97 5. Mobilization 6. Total Work Completed 359,140.97 7. Deductions 0.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 359,140.97 31,289.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,289.97